01 / COSTING
Estimate the real cost of a 3D print
Separate material, electricity, machine time and handling before quoting a job.
Start with the sliced model
Record the actual extrusion estimate, including brims, supports and purge. A generated model’s volume alone does not tell you how much filament the printer will use.
Keep hours and wages separate
Machine hours can run with little supervision. Measure setup and cleanup as handling time, then account for the printer and electricity on their own lines.
Price an expected outcome
Use a realistic failure estimate from comparable jobs. A retry rate is an assumption, not a guarantee. Write it down so a quote can be checked later.
Worked example: the material line is only the beginning
An illustrative 90 g attempt at $22 per kilogram contains $1.98 of filament before any separately counted waste. Two print hours at an average 95 W use 0.19 kWh; at $0.20 per kWh that is $0.038. Four hands-on minutes at $25 per hour add about $1.67 before machine allowance and failures. These are arithmetic examples, not measured printer specifications or a recommended selling price. The calculator keeps these lines separate so you can replace them with your own slicer report, electricity tariff and recorded handling time.
Define what one attempt includes
A failed attempt may stop early, while another consumes almost a complete print. The current calculator uses the same per-attempt assumptions across an expected attempt count; it does not know when your failures occur. Record that limitation beside the quote. Do not count the same brim or support twice if it is already included in the slicer grams. Likewise, do not charge a full hour of handling because the machine prints for an hour. Assign actual setup, removal and cleanup time to the part or plate that causes it.
Turn the estimate into a repeatable record
Export both scenarios before the job and retain the material profile, intended good quantity and failure assumption. After the run, record actual good parts, total material used, machine hours and hands-on minutes. Compare differences on the same basis rather than treating the forecast as evidence of performance. A quote also needs your own treatment of tax, delivery, packaging and profit; these are not silently included in a calculator labelled as production cost. The break-even worksheet explores a reserve separately and does not replace accounting advice.
Common questions
Does the calculated cost include profit and tax?
No. The production-cost comparison covers its labelled cost inputs. Add your own clearly specified commercial terms outside that calculation.
Can a generated model’s volume replace slicer grams?
No. Slicer extrusion includes choices such as perimeters, infill and supports that a solid geometry volume does not capture.
Sources and scope
Original planning guidance and labelled worked examples. These primary references support the technical context; our exercises and editable assumptions are not presented as official recommendations from these organisations.